2014-CSP-DPL-163 Wells to Harrington Rebuild

The CKT 6784 Rebuild consisted of rebuilding a 9.25 mile line, installing new poles, drilled pier foundations, caissions , conductor and OPGW while removing 132 wood poles , conductor and static.

Having prepared for non-outage conditions and increasing crew demands, the project was completed three weeks ahead of schedule.